Utility Relocation to Begin for Wrightsville Beach Bridge Replacements, July 17
- Wrightsville Beach Chamber of Commerce
- Jul 17
- 1 min read
From the North Carolina Department of Transportation, July 17 @ 10:19am:
Contract crews for the N.C. Department of Transportation are set begin utility relocation next week for the Wrightsville Beach Bridge Replacement project.
Starting Monday, July 20, crews will begin utility relocation by moving power poles near the West Salisbury Street (U.S. 74) bridge over Lee’s Cut. Most work will occur outside the travel lanes and is not expected to impact traffic. Should minor lane closures be required, they will be scheduled at night, and the public will be notified.
Utility relocation is a critical step in preparing the area for the replacement of the bridge. Work is expected to be complete by mid-August, weather permitting.
Drivers should slow down and watch for crews working in the area.
--
From the Chamber:
The Wrightsville Beach Bridge Replacements project (which will encompass many smaller projects and milestones) is an NCDOT project, not Town of Wrightsville Beach project. NCDOT is the outlet for all official communication. You can sign up to receive communication alerts via email and/or text message on the NCDOT Wrightsville Beach Replacements page at https://www.ncdot.gov/projects/wrightsville-beach-bridge-replacements/Pages/default.aspx